March, 2009
Back-filling for the station and platform sections.

May, 2009
The track as seen from the station platform. Construction of supports is underway.

June, 2009
Most of the platform supports are complete.

July, 2009
The track beams are almost up to the platform. You can see the layout of the platform.

September, 2009
The track beams are connected with the platform. The platform is steadily being completed.

December, 2009
The platform pillars are complete and the roof is being constructed.